SUPERIOR ENVIRONMENTAL PROVIDES HUGE SAVINGS FOR JARCHEM INDUSTRIES!

Wall Township, NJ  10/25/2012   Superior Environmental engineered, furnished, & installed (3) Webster JBS high turndown burners with Siemens linkageless Controls for Jarchem Industries in Newark NJ. The entire project was completely paid back in only 4 months after burner light-off. Jarchem converted from #4 fuel oil to natural gas. Superior Environmental designed the new natural gas supply piping, burner installation plan for the (3) existing firetube boilers, and the electrical configuration for the entire system. We were the engineers, mechanical contractors, burner representatives and start-up technicians; exactly the way we like to do things so they get done correctly. Give us a call if you would like to have Superior look at your next boiler or burner project. We get results and they are proven!